Deepening of the fairway of the Lower Main

  • Home
  • >
  • Projects
  • >
  • Deepening of the fairway of the Lower Main

Deepening of the fairway of the Lower Main

Posted by Viktoria Weissenburger, Friday, 28th September 2018 @ 4:10 pm


Basic  project  data 

Project ID: PA1A162  
Project website: http://www.bvwp-projekte.de/wasserstrasse/w30/w30.html (German)


Need  and  added  value  for  the  Danube  Region  Strategy

The Main is 524 km long, of which 388 km are navigable. The Main connects the Rhine and the Danube via the Main-Danube Canal and is therefore an important part of the inland waterway network of the Danube Region. Currently, the possible draught in the Main stretch between the Rhine mouth and Aschaffenburg is 2.9 m. All measures concerning the upgrade of the waterway infrastructure at the Main are thus beneficial for waterway transport in the entire Danube Region.

OBJECTIVE(S)  oF  the  PROJECT

Sole objective of this infrastructure project is the deepening of the fairway on the Lower Main between the Rhine mouth (rkm 0.0) and Aschaffenburg (rkm 84.5), in order to enable a draught of 3.1 m.


(c) German Ministry of Transport and digital Infrastructure

planned  project  activities

Capital dredging and hydrotechnical engineering.

transboundary  impact

The Main connects the Danube and the Rhine via the Main-Danube Canal. The result of the works will be an increase in transnational transports along the Rhine-Main-Danube axis.

Project  beneficiaries  /  target  groups

The waterway users and businesses operating in the Danube Region will be the main beneficiaries of the measures.
 

status  and  timeframe

Start date: 01/2015
End date: tbd

notes

The project is currently in the preliminary planning phase, the planning approval procedure has not yet started. Accordingly, an estimation about the start of actual works can not be given.  
 

Financing

Total budget: approx. 28 mn EUR (the project is part of the German “Bundesverkehrswegeplan” and is financed as one project of “priority need”)
The total amount is financed from national budget.
 

Project  team

Project leader: Wasserstraßen-Neubauamt Aschaffenburg / Germany (website: www.wsv.de)
Address: Hockstraße 10, 63743 Aschaffenburg / Germany
Contact data: wna-aschaffenburg@wsv.bund.de; +49 6021 312 - 0
 

Project  environment

Project  Cross - Reference

Deepening of the fairway of the Upper Main (PA1A157)

strategic  reference

Bundesverkehrswegeplan 2030

relevant  legislation

  • Bundeswasserstraßenausbaugesetz (WaStrAbG)
  • TEN-T guidelines
     

eusdr  embedding


 

eusdr  compliance


 

meta  data

Data provided by: viadonau (based on information from the project website and the TEN-T Corridor Study) - 25.09.2018